Specification for Hydraulically Bound Mixtures
for use in construction projects
What follows describes the framework for a specification that
has been developed for the production, construction and testing
of HBM. The full specification is similar to the 800 series
of the Specification for Highway Works (SHW). Unlike the SHW
however, it is applicable to the use of HBM for trench reinstatements
and non-road applications such as coastal protection as well
as for pavements. The full specification can be made available
on request.
XX0 General Requirements
Hydraulically
bound mixtures shall be produced, constructed and tested
in accordance with the following Clauses.
The permitted
HBM for the Works shall be shall be selected from BSEN 14227-1,
-2, -3, -5, -10, -11, -12, -13 & -14.
XX1 Constituents
XX2 Storage of constituents
XX3 General Requirements for Production and Construction
XX4 Mix-in-Plant Method of Construction Using Batching by
Mass
XX5 Mix-in-Plant Method of Construction Using Volume Batching
XX6 Mix-in-Place Method of Construction
XX7 Method Statement and Demonstration Area for All Methods
of Construction
XX8
HBM to BSEN 14227-1, 2, 3 & 5
XX9
HBM to BSEN 14227-10, -12, -13 & -14
XX10 Testing, Control and Checks for HBM
XX11 Laboratory Mixture Design procedure for HBM
|